| Client |
JSC "Ventspils Nafta" |
| Project |
Oil tank farm 6*20000m3 |
| Description of the works |
Assembly and anticorrosion treatment of the tanks. Assembly of the technological pipeline and equipment installation. General building works. |
Total cost (thous. LVL) |
1662,3 |
| |
| Client |
JSC "Ventspils Nafta" |
| Project |
Oil tank V=20000m3 |
| Description of the works |
Production, anticorrosion treatment and assembly of metal structures. |
Total cost (thous. LVL) |
25,9 |
| |
| Client |
JSC "Ventbunkers" |
| Project |
Technological pipeline |
| Description of the works |
Production, anticorrosion treatment and assembly of metal structures and the pipelines. |
Total cost (thous. LVL) |
297,2 |
| |
| Client |
JSC "Kalijas parks" |
| Project |
Storehouse facility for the potassium salt loading |
| Description of the works |
General building works. Assembly and anticorrosion treatment of metal structures. Technological equipment delivery and installation. |
Total cost (thous. LVL) |
2006,5 |
| |
| Client |
JSC "Ventspils Nafta" |
| Project |
Oil double-wall tank afrm 2*20000m3 |
| Description of the works |
Production, anticorrosion treatment and assembly of metal structures, heat-insulation. |
Total cost (thous. LVL) |
921,4 |
| |
| Client |
"Naftas Park" |
| Project |
Oil tank farm 4*10000m3 |
| Description of the works |
Anticorrosion treatment and assembly of metal structures. |
Total cost (thous. LVL) |
682 |
| |
| Client |
JSC "Brocini" |
| Project |
Reconstruction of kilns in the Broceni city |
| Description of the works |
Production, anticorrosion treatment and assembly of metal structures. |
Total cost (thous. LVL) |
275,8 |
| |
| Client |
JSC "Ventspils Nafta" |
| Project |
Industrial sewerage |
| Description of the works |
General building works. Installation of the technological lines and pumping plants, metal structures. |
Total cost (thous. LVL) |
174,2 |
| |
| Client |
JSC "Ventspils Nafta" |
| Project |
Heat pipeline L=2050m |
| Description of the works |
Assembly of the pipelines, heat-insulation. |
Total cost (thous. LVL) |
164,6 |
| |
| Client |
LatRosTrans Ltd. |
| Project |
Metering unit for oil products in the Ventspils city |
| Description of the works |
Assembly of the pipelines, equipment installation, heat-insulation. |
Total cost (thous. LVL) |
57,4 |
| |
| Client |
JSC "Ventbunkers" |
| Project |
Technological pipeline D=530mm |
| Description of the works |
Assembly of metal structures and technological pipelines. |
Total cost (thous. LVL) |
21,1 |
| |
| Client |
JSC "Ventspils Nafta" |
| Project |
Oil tank farm 5*20000m3 |
| Description of the works |
Production, anticorrosion treatment and assembly of metal structures, heat-insulation. |
Total cost (thous. LVL) |
185,7 |
| |
|
|
|